Production plan for welding and painting of chassis at the Mexico factory 2024.10.01
Due to the request from Central Company (China), the plant in Mexico must complete the welding and painting work on all existing chassis before December 1st. Therefore, this plan is being developed.
Production requirements: Complete the welding, shot blasting, and painting of the chassis before December.
Production Deadline: 2024.10.01 2024.12.01
Actual working days: 8 weeks / 40 days
1. Welding Work Plan
Work unit
Unidad de
trabajo| Unidad de |
| :---: |
| trabajo |
Number of chassis pending completion
Cantidad de chasis
pendientes de
completar| Cantidad de chasis |
| :---: |
| pendientes de |
| completar |
Quantity produced per day
Cantidad
producida por
día| Cantidad |
| :---: |
| producida por |
| día |
Necessary working days
Días laborables
necesarios| Días laborables |
| :---: |
| necesarios |
Expected completion date
Fecha prevista de
finalización| Fecha prevista de |
| :---: |
| finalización |
Welders are needed
Se necesitan
soldadores| Se necesitan |
| :---: |
| soldadores |
welding
450
30
15 days
2024.10 .25
16 Pers.
"Unidad de
trabajo" "Cantidad de chasis
pendientes de
completar" "Cantidad
producida por
día" "Días laborables
necesarios" "Fecha prevista de
finalización" "Se necesitan
soldadores"
soldadura 450 30 15 días 2024.10 .25 16 Pers.| Unidad de <br> trabajo | Cantidad de chasis <br> pendientes de <br> completar | Cantidad <br> producida por <br> día | Días laborables <br> necesarios | Fecha prevista de <br> finalización | Se necesitan <br> soldadores |
| :---: | :---: | :---: | :---: | :---: | :---: |
| soldadura | 450 | 30 | 15 días | 2024.10 .25 | 16 Pers. |
Currently, the 16 welders can meet the production requirements. There is no problem completing the welding jobs within the month of October.
When the welding work is finished, the welder may be pulled to another job.
2. Shot Blasting Work Plan
Work unit
Number of chassis pending completion
Cantidad de chasis
pendientes de
completar| Cantidad de chasis |
| :---: |
| pendientes de |
| completar |
Quantity produced per day
Cantidad
producida por
día| Cantidad |
| :---: |
| producida por |
| día |
Necessary working days
Días laborables
necesarios| Días laborables |
| :---: |
| necesarios |
Expected completion date
Fecha prevista de
finalización| Fecha prevista de |
| :---: |
| finalización |
Number of people needed
Cantidad de
personas
necesarias| Cantidad de |
| :---: |
| personas |
| necesarias |
shot blasting
788
30
27 days
///
5 Pers.
Unidad de trabajo "Cantidad de chasis
pendientes de
completar" "Cantidad
producida por
día" "Días laborables
necesarios" "Fecha prevista de
finalización" "Cantidad de
personas
necesarias"
granallado 788 30 27 天 // 5 Pers.| Unidad de trabajo | Cantidad de chasis <br> pendientes de <br> completar | Cantidad <br> producida por <br> día | Días laborables <br> necesarios | Fecha prevista de <br> finalización | Cantidad de <br> personas <br> necesarias |
| :---: | :---: | :---: | :---: | :---: | :---: |
| granallado | 788 | 30 | 27 天 | $/$ | 5 Pers. |
Schedule shot blasting of the frame every Monday, Tuesday, and Wednesday. On Thursday, Friday, and Saturday, shot blast subcontracted parts.
The shot blaster cannot be stopped; the requirement is to shot blast every day, and the shot blasting personnel cannot be moved.
At least 80 shot-blasted chassis must be processed per week to complete the production task on time.
3. Paint Production Plan
Work unit
Number of chassis pending completion
Cantidad de
chasis
pendientes de
completar| Cantidad de |
| :---: |
| chasis |
| pendientes de |
| completar |
Quantity produced per day
Cantidad
producida por
día| Cantidad |
| :---: |
| producida por |
| día |
Necessary working days
Días laborables
necesarios| Días laborables |
| :---: |
| necesarios |
Expected completion date
Fecha prevista de
finalización| Fecha prevista de |
| :---: |
| finalización |
Number of painters needed
Cantidad de
pintores
necesarios| Cantidad de |
| :---: |
| pintores |
| necesarios |
painting
788
20
40
2024.12 .05
6
Unidad de trabajo "Cantidad de
chasis
pendientes de
completar" "Cantidad
producida por
día" "Días laborables
necesarios" "Fecha prevista de
finalización" "Cantidad de
pintores
necesarios"
pintura 788 20 40 2024.12 .05 6| Unidad de trabajo | Cantidad de <br> chasis <br> pendientes de <br> completar | Cantidad <br> producida por <br> día | Días laborables <br> necesarios | Fecha prevista de <br> finalización | Cantidad de <br> pintores <br> necesarios |
| :---: | :---: | :---: | :---: | :---: | :---: |
| pintura | 788 | 20 | 40 | 2024.12 .05 | 6 |
The current number of painters is 3, and 3 more are needed.
Since shot blasting and painting are continuous operations, the painting employees must take care of the cleaning of the chassis and the painting work on a daily basis…
The painting staff positions are fixed and non-transferable.
At least 80 chassis must be painted per week to complete the production task on time.
Notes and Comments
In summary, to fulfill the production task of the Central Company (China), 25 employees are needed in permanent positions.