9月27日-10月4日工作计划
Work plan from September 27 to October 4
9月27日
September 27th
从停车场,用平板拖车转运材料和部分灯组到新草坪区域(平板拖车)
From the parking lot, transfer of materials and part of the light cluster with a flatbed trailer to the new lawn area (flatbed trailer)
四方广场—城堡正门整块区域的扫线工作
Square Square - sweeping the entire area of the main entrance of the castle
新草坪区域的游览路线确定及灯组定点位工作
The tour route of the new lawn area is determined and the lighting group is fixed
河边灌木满天星装饰工作
Riverside shrubs full of stars decoration work
9月28日
September 28th
卸集装箱,转运材料到新草坪区域(叉车)
Unloading containers and transferring materials to the new lawn area (forklifts)
新草坪区域开始司母戊鼎的主骨架焊接(叉车)
The main skeleton welding of Simu Wuding began in the new lawn area (forklift)
新草坪区域扫线工作
Sweeping work in the new lawn area
9月29日
September 29th
新草坪区域司母戊鼎的主骨架焊接(叉车)
The main skeleton welding of the new lawn area Simu Wuding (forklift)
从停车场工棚转运灯组新草坪区域(平板车、卡车)
Transfer of light groups from the parking shed to the new lawn area (flatbed, truck)
继续四方广场—城堡正门整块区域的扫线工作
Continue the sweeping work on the entire area of the square square - the main entrance of the castle
安装游客中心周边商铺及建筑物上串灯泡
Install light bulbs on shops and buildings around the visitor center
9月30日
September 30th
新草坪区域司母戊鼎的主骨架焊接(叉车)
The main skeleton welding of the new lawn area Simu Wuding (forklift)
四方广场两个通道拱门的找平工作(打桩、焊接)。
Leveling of the arches of the two passages in the square square (piling, welding).
从停车场运输灯组到四方广场及糖果商店处等待安装(平板车、卡车)
Transport of light clusters from the parking lot to the square plaza and confectionery store for installation (flatbed, truck)
安装游客中心周边商铺及建筑物上串灯泡
Install light bulbs on shops and buildings around the visitor center
水泥墩子到达四方广场
The cement pier arrives at the square square
10月1日
October 1
新草坪区域司母戊鼎的主骨架焊接(叉车)
The main skeleton welding of the new lawn area Simu Wuding (forklift)
四方广场和糖果商店区域灯组运输及安装(打桩、焊接、平板车、叉车)
Transportation and installation of light clusters in the square square and confectionery store area (piling, welding, flatbed, forklift)
四方广场射灯安装(打桩)
Square Square Spotlight Installation (Piling)
从停车场运输灯组到城堡背后的河边(平板车、卡车)
Transportation of light clusters from the parking lot to the riverside behind the castle (flatbed, truck)
安装游客中心周边商铺及建筑物上串灯泡
Install light bulbs on shops and buildings around the visitor center
10月2日
October 2nd
新草坪区域司母戊鼎的主骨架焊接(叉车、工程车)
Welding of the main skeleton of the new lawn area (forklifts, engineering vehicles)
新草坪区域金字塔灯组内部钢管架子钢管搭建(打桩)
New lawn area pyramid light group internal steel pipe frame steel pipe construction (piling)
新草坪区域大灯组找平工作(打桩、焊接)
New lawn area headlight group leveling work (piling, welding)
水边安装维京时代及中国题材陆地灯组(打桩、焊接)
Installation of Viking Age and Chinese-themed land lamps at the water's edge (piling, welding)
完成圣诞12天扫线工作
Complete the 12 days of Christmas sweeping work
10月3日
October 3rd
新草坪区域司母戊鼎的主骨架焊接(叉车、工程车)
Welding of the main skeleton of the new lawn area (forklifts, engineering vehicles)
新草坪区域金字塔灯组内部钢管架子钢管搭建(打桩)
New lawn area pyramid light group internal steel pipe frame steel pipe construction (piling)
新草坪区域大灯组找平工作(打桩、焊接)
New lawn area headlight group leveling work (piling, welding)
从停车场运输灯组到新草坪区域(平板车、卡车)
Transport of light clusters from the parking lot to the new lawn area (flatbeds, trucks)
运输并安装圣诞12天(平板车、打桩)
Transportation and installation of the 12 Days of Christmas (flatbed, piling)
10月4日
October 4th
新草坪区域司母戊鼎的主骨架焊接(叉车、工程车)
Welding of the main skeleton of the new lawn area (forklifts, engineering vehicles)
新草坪区域金字塔灯组内部钢管架子钢管搭建(打桩)
New lawn area pyramid light group internal steel pipe frame steel pipe construction (piling)
新草坪区域大灯组找平工作(打桩、焊接)
New lawn area headlight group leveling work (piling, welding)
从停车场运输灯组到新草坪区域(平板车、卡车)
Transport of light clusters from the parking lot to the new lawn area (flatbeds, trucks)